top of page
  • Writer's pictureH. Sterling Group

Yantai LNG Updates

By October 30, 2021, Yantai LNG has completed 30.50% of the total workload of the project. The bearing platform construction in the storage tank farm was completed, and the first wall construction of each storage tank is being carried out as planned. The procurement of project equipment has completed 20% of the total plan, and the foundation construction is under way in the regasification area of the project, accounting for 95% of the total work. The 3D model of the project process has passed the expertsreview.











Comments


bottom of page